Analisis Kelayakan Proyek Pembangunan Pltm Walesi Cascade Secara Nilai Ekonomi Ketenagalistrikan Dan Potensi Kredit Karbon
Abstract
FEASIBILITY ANALYSIS OF THE WALESI CASCADE MINI-HYDROPOWER DEVELOPMENT PROJECT IN TERMS OF POWER SECTOR ECONOMIC VALUE AND CARBON CREDIT POTENTIAL
The development of the Walesi Cascade Mini Hydropower Plant (PLTM) in Jayawijaya Regency, Papua Province, represents a strategic initiative in supporting Indonesia’s energy transition agenda toward achieving the Net Zero Emission (NZE) 2060 target. As part of the renewable energy mix, mini hydropower has significant potential to reduce dependence on fossil fuels, enhance regional energy resilience, and lower carbon emissions in the electricity sector. This study aims to evaluate the economic feasibility and carbon trading potential of the Walesi Cascade PLTM, while assessing its contribution to clean energy provision and climate change mitigation. The economic analysis utilizes several key indicators. The Levelized Cost of Energy (LCOE) is used to assess total electricity generation costs and demonstrates competitive cost efficiency. The financial analysis shows a positive Net Present Value (NPV), indicating that the project’s benefits outweigh its investment costs. The high Internal Rate of Return (IRR) reflects an attractive investment return. Additionally, the Break-Even Point (BEP) is estimated to be achieved in approximately 8.9 years, and the Benefit-Cost Ratio (BCR) greater than 1 signifies that the economic benefits substantially exceed total expenditures. A favorable Rate of Return (RoR) further strengthens the long-term financial sustainability of the project. From an environmental perspective, this study identifies opportunities for carbon trading through the Voluntary Carbon Market (VCM). The potential generation of carbon credits from emission reductions in the Walesi Cascade PLTM plays an important role in accelerating Indonesia’s transition toward sustainable clean energy.
Keywords
References
A. Taufiqurrahman and J. Windarta, “Overview Potensi dan Perkembangan Pemanfaatan Energi Air di Indonesia,” Jurnal Energi Baru dan Terbarukan, vol. 1, no. 3, 2020, doi: 10.14710/jebt.2020.10036.
F. Mandasari, S. Marsudi, and Moh. Sholichin, “Studi Manajemen Pelaksanaan Konstruksi Bendung Pltm Prafi Kecamatan Warmare Kabupaten Manokwari Provinsi Papua Barat dengan Menggunakan Microsoft Project Manager 2013,” Jurnal Teknologi dan Rekayasa Sumber Daya Air, vol. 3, no. 1, 2023, doi: 10.21776/ub.jtresda.2023.003.01.08.
F. Mandasari, S. Marsudi, and Moh. Sholichin, “Studi Manajemen Pelaksanaan Konstruksi Bendung Pltm Prafi Kecamatan Warmare Kabupaten Manokwari Provinsi Papua Barat dengan Menggunakan Microsoft Project Manager 2013,” Jurnal Teknologi dan Rekayasa Sumber Daya Air, vol. 3, no. 1, 2023, doi: 10.21776/ub.jtresda.2022.003.01.08.
B. A. Pratama, M. A. Ramadhani, P. M. Lubis, and A. Firmansyah, “Implementasi Pajak Karbon Di Indonesia: Potensi Penerimaan Negara Dan Penurunan Jumlah Emisi Karbon,” JURNAL PAJAK INDONESIA (Indonesian Tax Review), vol. 6, no. 2, 2022, doi: 10.31092/jpi.v6i2.1827.
Y. Zhou, “Worldwide carbon neutrality transition? Energy efficiency, renewable, carbon trading and advanced energy policies,” 2023. doi: 10.1016/j.enrev.2023.100026.
A. R. Muhammad and S. M. Damayanti, “Financial Feasibility Analysis of Gumanti Micro Hydro Power Plant Project,” Jurnal Of Business And Managemen, vol. 4, no. 3, 2015.
C. B. Amougou, D. Tsuanyo, D. Fioriti, J. Kenfack, A. Aziz, and P. Elé Abiama, “LCOE-Based Optimization for the Design of Small Run-of-River Hydropower Plants,” Energies (Basel), vol. 15, no. 20, 2022, doi: 10.3390/en15207507.
Moh. Sofyan and I. M. Sudana, “Analisis Potensi Pembangkit Listrik Tenaga Mikro Hidro (PLTMH) Berdasarkan Debit Air dan Kebutuhan Energi Listrik,” Jurnal Listrik, Instrumentasi, dan Elektronika Terapan, vol. 3, no. 2, 2022, doi: 10.22146/juliet.v3i2.64410.
L. N. Rahayu and J. Windarta, “Tinjauan Potensi dan Kebijakan Pengembangan PLTA dan PLTMH di Indonesia,” Jurnal Energi Baru dan Terbarukan, vol. 3, no. 2, 2022, doi: 10.14710/jebt.2022.13327.
Rizdam Firly Muzakki, “STUDI POTENSI PEMBANGKIT LISTRIK TENAGA MIKRO HIDRO (PLTMH) DI PULAU TIMOR, NUSA TENGGARA TIMUR,” Jurnal Rekayasa Elektro Sriwijaya, vol. 4, no. 2, 2023, doi: 10.36706/jres.v4i2.81.
J. A. , & R. M. A. Sánchez, “Feasibility study of a micro-hydro power plant in a rural area of Colombia: Technical, economic, and environmental analysis,” Renewable Energy, 104, 498-506., 2017.
B. K. Ahmad Wibowo, “Kajian Potensi Pembangkit Listrik Tenaga Mikro Hidro di Sungai Air Kule Kabupaten Kalur,” Jurnal Teknik Sipil, 2016.
D. H. S. Catur S. Dewi, “Analisis Kelemahan dan Kelebihan Pembangkit Listrik Tenaga Mikro Hidro,” Kumparan Fisika, 2020.
F. M. Muhammad Basyir, “Analisis Keberlanjutan Sosial dan Ekonomi pada Pembangkit Listrik Tenaga Mikro Hidro (PLTMH),” Jurnal Pembangunan Ekonomi, 2021.
N. F. Rudi Hartono, “Studi Potensi Pembangkitan Listrik Tenaga Mikro Hidro di Pulau Timor,” Jurnal Rekayasa Elektro Sriwijaya, 2022.
H. C. Dwi Kurniawan, “Implementasi Perdagangan Emisi Karbon dalam Rangka Mitigasi Perubahan Iklim ,” Jurnal Analisis Kebijakan Kehutanan, 2023.
K. P. Adi P. Wibowo, “Kajian Pembangkitan Energi Terbarukan dari PLTMH di Daerah Aliran Sungai Citarum,” Jurnal Energi dan Lingkungan, 2020.
T. A. B. K. Wardana and C. A. Siregar, “ANALISIS PERENCANAAN PONDASI DINAMIS UNTUK MENDUKUNG MESIN TURBIN PADA PLTM WARNASI DI MANOKWARI, PROVINSI PAPUA BARAT,” Sistem Infrastruktur Teknik Sipil (SIMTEKS), vol. 2, no. 1, 2022, doi: 10.32897/simteks.v2i1.1539.
T. Jaelani and E. Walujodjati, “Analisis dan Desain Power House Proyek PLTM Cikandang 1 Pakenjeng Garut,” Jurnal Konstruksi, vol. 19, no. 2, 2022, doi: 10.33364/konstruksi/v.19-2.880.
M. , & H. A. Syam, “Perencanaan PLTM Palumbungan, Purbalingga,” Jurnal Teknik Energi, 5(2), 75-82. Institut Teknologi PLN, 2020.
B. , & P. P. Setiono, “Simulasi dinamis dalam pembangkit listrik tenaga mikrohidro dengan menggunakan model analisis sistem energi,” Jurnal Energi Terbarukan, 14(1), 100-110. Institut Teknologi PLN, 2020.
S. Kurniawan, “Analisis kinerja sistem PLTM terhadap variasi debit aliran sungai di Indonesia,” Jurnal Teknologi Energi, 11(2), 135-145. Institut Teknologi PLN, 2022.
R. , & H. A. Putra, “Pemodelan sumber energi mikrohidro untuk pembangkit listrik tenaga mikrohidro (PLTM),” Jurnal Energi Terbarukan, 10(1), 130-140. Institut Teknologi PLN, 2021.
A. Sidqi, “Analisa kualitas penyaluran daya pada sistem 20 kV Painan terhadap interkoneksi dengan PLTM Lumpo 3 MW,” Jurnal Teknologi Energi, 7(3), 256-265. Institut Teknologi PLN, 2021.
I. , & F. R. Wahyu, “Analisa daya PLTM Tukad Balian, Tabanan menggunakan simulink,” Jurnal Teknik Mesin, 7(2), 54-62. Institut Teknologi PLN, 2020.
B. Gudlaugsson, T. G. Ahmed, H. Dawood, C. Ogwumike, M. Short, and N. Dawood, “Cost and environmental benefit analysis: An assessment of renewable energy integration and smart solution technologies in the InteGRIDy project,” Cleaner Energy Systems, vol. 5, 2023, doi: 10.1016/j.cles.2023.100071.
M. León, J. Silva, R. Ortíz-Soto, and S. Carrasco, “A Techno-Economic Study for Off-Grid Green Hydrogen Production Plants: The Case of Chile,” Energies (Basel), vol. 16, no. 14, 2023, doi: 10.3390/en16145327.
S. Sung and W. Jung, “Economic competitiveness evaluation of the energy sources: Comparison between a financial model and levelized cost of electricity analysis,” Energies (Basel), vol. 12, no. 21, 2019, doi: 10.3390/en12214101.
G. G. Dranka, J. Cunha, J. D. de Lima, and P. Ferreira, “Economic evaluation methodologies for renewable energy projects,” AIMS Energy, vol. 8, no. 2, 2020, doi: 10.3934/ENERGY.2020.2.339.
Mardelin Kastela, B. Widodo, and R. Purba, “Perancangan Pembangkit Listrik Tenaga Hibrida (PLTS Dan PLTMH-GRID) Di Desa Tiworiwu I Dan Desa Bea Pawe, Kabupaten Ngada, Nusa Tenggara Timur (NTT),” Lektrokom : Jurnal Ilmiah Teknik Elektro, vol. 6, no. 2, 2023, doi: 10.33541/lektrokom.v6i2.5173.
S. Suandi and N. Chayati, “Studi Kelayakan Finansial pada Proyek Pembangunan Pembangkit Listrik Tenaga Minihidro (PLTM ) Pongkor,” Seminar Nasional Sains dan Teknologi 2018, vol. 1, no. 1, 2018.
S. Baurzhan, G. P. Jenkins, and G. O. Olasehinde-Williams, “The economic performance of hydropower dams supported by the world bank group, 1975–2015,” Energies (Basel), vol. 14, no. 9, 2021, doi: 10.3390/en14092673.
D. Djaenudin, M. Lugina, and G. Kartikasari, “The Forest Carbon Market Implementation Progress in Indonesia,” Jurnal Analisis Kebijakan, vol. 13, no. December, 2016.
M. Rumbayan and K. Nagasaka, “Emission And Financial Analysis Of Geothermal Energy Resource (The Case Of Lahendong Site In Indonesia),” International Journal of Engineering Research and Applications (IJERA), vol. 2, no. august, 2012.
B. Shi, N. Li, Q. Gao, and G. Li, “Market incentives, carbon quota allocation and carbon emission reduction: Evidence from China’s carbon trading pilot policy,” J Environ Manage, vol. 319, 2022, doi: 10.1016/j.jenvman.2022.115650.
Kemeterian ESDM, “Penuhi Kebutuhan Listrik 2060 dan Capai NZE, Kementerian ESDM Optimalkan Pemanfaatan Energi Bersih,” 2021.
PT. PLN (Persero), “Feasibility Study Pekerjaan Jasa Penyusunan Studi Kelayakan PLTM Walesi Cascade,” FS PUSHARLIS, 2021.
PT. PLN Persero, “Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) PT PLN (Persero) 2021-2030,” 2021.
M. Wongphat and S. Premrudeepreechacharn, “Evaluation of engineering and economic feasibility of micro-hydropower plant project,” in IYCE 2015 - Proceedings: 2015 5th International Youth Conference on Energy, 2015. doi: 10.1109/IYCE.2015.7180813.
V. Firmansyah, M. K. Adinarayana, R. Tetrisyanda, and G. Wibawa, “Scenario of renewable energy transition from fossil energy resources towards net zero emission in Indonesia,” in E3S Web of Conferences, 2023. doi: 10.1051/e3sconf/202346704005.
DOI: 10.33751/jmp.v14i1.13049